At the leading edge of repair

Chloe Hirst, senior copywriter at Belzona, the polymer repair composites and industrial protective coatings specialists, examines the role of polymeric technology in the burgeoning wind power industry.

There has been considerable growth in the wind power industry over the past few years. However, further exponential growth of the industry is required in order to ensure that the net-zero by 2050 pathway - as outlined in the Paris Agreement - is successfully reached.

In order to support this seismic growth, polymeric repair and protection technology has an important part to play. Designed to safeguard the integrity of wind turbine blade leading edges for the long term, this technology plays a critical role in supporting this burgeoning industry.

According to the International Energy Association’s (IEA) Wind Electricity Tracking Report (September 2022): “In 2021 wind electricity generation increased by a record 273TWh (up 17%). This was 55% higher growth than that achieved in 2020 and was the highest among all renewable power technologies.”

Leading edge damaged by erosion
Leading edge damaged by erosion

While the industry has undoubtedly experienced impressive levels of growth in these years, according to the IEA, wind electricity generation needs to reach four times the record levels set in 2020 by 2030. The Report said: “Our pathway calls for scaling up solar and wind rapidly this decade, reaching annual additions of […] 390GW of wind by 2030”.

How is the Scale-Up of the Wind Industry Being Financed? According to the IEA’s Report: “Policy support remains the principal driver of wind deployment in the majority of the world.” Indeed, over the past few years, several policies have been launched that are designed to drive forward the roll-out of renewables.

For example, in August 2022, the US brought in the Inflation Reduction Act (IRA) which includes $369 billion of investment, in the European Commission’s Green Deal Industrial Plan, $270 billion was pledged, and since the UK government’s Ten Point Plan was launched in November 2020, over £26 billion of government capital investment has been mobilised.

A material whirl

Given the critical role wind power plays in the transition to a net-zero future, as well as the significant amount of capital being invested into the renewables industry, the wind power sector is poised to experience considerable exponential growth in the upcoming decades. In order to support this growth, polymeric technology plays a significant role when it comes to maintaining the operational efficiency of the rapidly expanding fleets of wind turbines.

Polymeric systems, such as the rebuild, blade filler material, Belzona 5711 and the cartridge-applied leading edge protection coating, Belzona 5721, are specially designed to repair damaged leading edges and protect them against rain erosion and impact damage for the long term.

Surface preparation using an orbital sander
Surface preparation using an orbital sander

In addition to the performance capabilities of these systems, maintenance engineers are investing in this technology due to the simple, in-situ application method and fast cure times the cold-curing systems facilitate. In turn, this helps to keep downtime to a minimum, and allows the turbine to be returned to service in the same day.

Belzona 5711 can be directly overcoated with Belzona 5721 in as little as 30 minutes at 20°C/68°F without the need for any additional surface preparation. At the same temperature, Belzona 5721 will be fully cured within five hours.

Belzona successfully addressed the wind turbine blade damage issue at Electricity Generating Authority of Thailand’s (EGAT) Khao Yai Thiang Windfarm in Thailand. The windfarm features wind turbines with 40m-long blades. During routine inspection, evidence of damage measuring 300cm x 14cm x 2mm on the leading edge of one of the blades was discovered.

Representatives from the 35-year-old Belzona Authorised Distributorship, Pan Mechanic Engineering, recommended the solvent-free, two-part repair paste, Belzona 5711 to reconstruct the damaged area on the blades, followed by the high-performance coating, Belzona 5721, to overcoat the area.

Application procedure

The application procedure involved surface preparation using an orbital sander, followed by the direct application of approximately 1.4kg of Belzona 5711 from a self-mixing cartridge onto the blade. The repair area was contoured using a piece of Belzona mixing board.

After a two-hour curing period, a visual inspection was conducted to ensure the application's readiness for overcoating with approximately 3.5kg of Belzona 5721. Using a short-bristled brush, this system was then applied to the leading edge and left to cure. The blade was back in service 24 hours later.

EGAT's technicians were trained at the Belzona Asia Pacific facility to perform the application, with two representatives from Belzona's Technical Service Department present on site to observe and provide guidance.

Commenting on the application, an EGAT representative said: “We are extremely satisfied with the results achieved by Belzona's leading edge repair and protection system. The application procedure was very simple, and could be carried out quickly, which ensured that downtime was kept to a minimum. We plan to place an order for more Belzona 5711 and Belzona 5721.”

In order to support the seismic growth of the wind power sector, polymeric technology, such as Belzona 5711 and Belzona 5721, plays a critical role. By safeguarding the integrity of wind turbine blades, this helps to keep windfarms functioning at their optimum efficiency, which in turn, supports a net-zero by 2050 pathway for the planet.

www.belzona.com

Related Articles

Hybrid benefits

An adhesive-free way of joining aluminium and composite parts – already proven in an industry project – is now becoming a commercial reality. Lou Reade reports.
6 years ago Features
Most recent Articles

Editor's comment: Weather with you

My work office feels unusually cold. As I type this, the BBC weather says it’s 10˚C outside. Hmm, is that typical for the end of April? Anyway, our landlord has deemed that with Spring now in the air, it’s time to turn off the heating and save money. This presents a challenge typing when I can’t feel my fingers.
2 days ago Features

The stage is all set!

Composites UK has added the Farnborough International Airshow to its portfolio of pavilions at shows for 2024. The Association’s marketing and communications manager, Claire Whysall explains why it’s the next logical step in the development of a wider programme of exhibition opportunities.
2 days ago Features

Login / Sign up